Wednesday, October 27, 2010

Slab progress

So I went to site again today and the progress has been good. The underslab drainage, sandbeds, membrane and trenching are done. Piles have been started, some formwork and some reo is in. The void formers and reo are on site and ready to go.

Slab making progress
 The main purpose for going to site this afternoon was to make sure that the extra piles we payed for had been put in prior to them pouring the slab. Here is a picture of our $700 holes :-)


Drilled holes for the piles


The slab is scheduled to be poured tomorrow - good luck with that one PH. I cant see them pouring the slab tomorrow but am hopeful given the speed that they seem to get things done that we should have something by the weekend.